Revision of Order Up! Planning/Time from Fri, 2013-03-15 22:53

PDF versionPDF version
Matching

Put the following Planning/Time Processes in the correct order

SubquestionCorrect matchFeedback
Define Activities1Yes, you must define before anything else
Sequence Activities2Correct, once defined, activities should be properly sequenced
Estimate Activity Resources3Once the definition and sequencing are correct, a PM should gather estimates on activity resources
Estimate Activity Duration4Once activities have been defined, sequenced and resources estimated, the duration of the activities is calculated
Develop Schedule5Developing a dschedule is the last sep of this area, since all other steps are required to provide the data necessary for a complete scheduling effort.