MC: Planning/Scope

Multiple choice question
Which of the following is NOT part of the Planning/Scope processes?
![]() | Create WBS |
![]() | Define Activities |
![]() | Define Scope |
![]() | Collect Requirements |
- Login to post comments
- Printer-friendly version
PDF version
Which of the following is NOT part of the Planning/Scope processes?
![]() | Create WBS |
![]() | Define Activities |
![]() | Define Scope |
![]() | Collect Requirements |