Put the following Planning/Time Processes in the correct order
Subquestion | Correct match | Feedback |
---|---|---|
Define Activities | Step 1 | Yes, you must define before anything else |
Sequence Activities | Step 2 | Correct, once defined, activities should be properly sequenced |
Estimate Activity Resources | Step 3 | Once the definition and sequencing are correct, a PM should gather estimates on activity resources |
Estimate Activity Duration | Step 4 | Once activities have been defined, sequenced and resources estimated, the duration of the activities is calculated |
Develop Schedule | Step 5 | Developing a dschedule is the last sep of this area, since all other steps are required to provide the data necessary for a complete scheduling effort. |