Directions: Move your mouse over the red + in the grey area beneath each of the sections below to reveal the exam data. Click on one of the two entries in the upper right box for the next flashcard. | Hide Answers
Next Card
Next Card (show answers) |
||
PROCESS GROUP | PROCESS NAME | KNOWLEDGE AREA | |
+
|
+ Develop Schedule |
+ Time |
|
Tool/Technique or Output? | Tool/Technique or Output | ||
+ Output |
Project schedule | ||
KEY INPUTS | Definition | KEY OUTPUT | |
+
|
+ Analyzing activity sequences, durations, resource reqts, and schedule constraints to create the project schedule |
+ Project schedule |
|
This was entry #469 -- Additional information is available in Section 6.5.3.1 of the PMBOK. |