PROCESS GROUP PROCESS NAME KNOWLEDGE AREA
Planning Time
Definition
Estimating the type and quantities of resources required to perform each activity
KEY INPUTS TOOL vs TECHNIQUE KEY OUTPUT
  • Activity attributes
  • Activity list
  • Enterprise environmental factors
  • Organizational process assets
  • Resource calendars
  • Alternatives analysis
  • Bottom-up estimating
  • Expert judgment
  • Project management software
  • Published estimating data
  • Activity resource requirements
  • Project document updates
  • Resource breakdown structure
This was entry #495 -- Additional information is available in Section 6.3.1.1 of the PMBOK.