PROCESS GROUP PROCESS NAME KNOWLEDGE AREA
Planning Time
Definition
Approximating the number of work periods needed to complete individual activities with estimated resources
KEY INPUTS TOOL vs TECHNIQUE KEY OUTPUT
  • Activity attributes
  • Activity list
  • Activity resource requirements
  • Enterprise environmental factors
  • Organizational process assets
  • Project scope statement
  • Resource calendars
  • Analogous estimating
  • Expert judgment
  • Parametric estimating
  • Reserve analysis
  • Three-point estimates
  • Activity duration estimates
  • Project document updates
This was entry #490 -- Additional information is available in Section 6.4.2.1 of the PMBOK.