There are a few key terms and formulas that you will need to have for the test.

CV = Cost Variance
SV = Schedule Variance
AC = Actual Costs
PV = Planned Value
==============

CV = EV - AC

SV = EV - PV

SPI = EV / PV

CPI = EV / AC

EAC = BAC / CPI

ETC = EAC - AC

VAC = BAC - EAC

TCPI = (BAC - EV) / (BAC - AC)

==============

PERT Estimates = D = (P + 4M + O) / 6

Communication Channels = (n(n-2)) / 2


Click the image for a larger picture