There are a few key terms and formulas that you will need to have for the test.
CV = Cost Variance
SV = Schedule Variance
AC = Actual Costs
PV = Planned Value
==============
CV = EV - AC
SV = EV - PV
SPI = EV / PV
CPI = EV / AC
EAC = BAC / CPI
ETC = EAC - AC
VAC = BAC - EAC
TCPI = (BAC - EV) / (BAC - AC)
==============
PERT Estimates = D = (P + 4M + O) / 6
Communication Channels = (n(n-2)) / 2
Click the image for a larger picture