MG: HR / Executing processes (Order Test)

PDF versionPDF version
Matching

Put the following processes in the correct order for the Executing / Human Resources Group

SubquestionCorrect matchFeedback
Acquire Project TeamStep 1The team must be acquired first
Develop Team ProjectStep 2In this case, "develop" is a means of improving, as opposed to building, the project team
Manage Project TeamStep 3In this case, "manage" is the long-term task
Develop Human Resource PlanNoneThis step actually falls under the "Planning" Process Group, not "Executing"